- Finished off and printed off third revision of transformer drawing - 0.5 hour
- Input cable length data into computer model for two stations (White City, West Souris) - 1 hour
- Worked on gathering cable data based on new drawings for the Sarnia, Bethune, Edmonton, Milden & Cromer stations - 3 hours
- Administrative - printing off drawings, installing and troubleshooting programs (MathCAD, SKM Powertools for Windows) - 3.5 hours
Monday, July 17, 2006
Day 20
Friday, July 14, 2006
Thursday, July 13, 2006
Wednesday, July 12, 2006
Tuesday, July 11, 2006
Day 16
- Administrative upkeepings - 0.5 hour
- Preparation for trip to site - 0.5 hour
- Work on drawings that needed to be re-requested - .5 hour
- Accompanied Jeff to visit PowerTran to work on three jobs. One was confirmed as near complete, another we spent 3 hours confiming connections of electrical components in a control cabinet, and another 5 hours was spent drawing out and getting the various dimensions for a transformer and it's components.
Monday, July 10, 2006
Thursday, July 06, 2006
Wednesday, July 05, 2006
Tuesday, July 04, 2006