Monday, July 17, 2006

Day 20
  • Finished off and printed off third revision of transformer drawing - 0.5 hour
  • Input cable length data into computer model for two stations (White City, West Souris) - 1 hour
  • Worked on gathering cable data based on new drawings for the Sarnia, Bethune, Edmonton, Milden & Cromer stations - 3 hours
  • Administrative - printing off drawings, installing and troubleshooting programs (MathCAD, SKM Powertools for Windows) - 3.5 hours